Progress of the Project
Progress of the Project
- Sialkot Tennery Zone is indispensable for the survival and upgradation of the Leather Sector of Pakistan.
- Sialkot city is fetching Major part of foreign exchange in Leather Sector.
- Sialkot Tannery Zone infrastructure ready to house the Tanneries in the Zone.
- Effluent Treatment of STZ is first of its kind in Pakistan have seprate primary treatment for beam house effluent and post Tanning effluent, which is 83% already completed. The installation of machines and equipment is in progress.
- The drainage system is 100% complete. All the drains are constructed in connecte to have a long life. The total length of drains is 35 km with segregated channels to carry beam house, chrome, and post Tanning effluents.
- The road structure having a length of 15 KM is complete, and only the black top is left.
- The solid waste management is part of STZ, the technology of hazardous management landfill is already firmed up.
- Construction on 225 plots is in progress.
- There are a total 540 plot holders in STZ, 90% are SMEs having plot sizes of 01 Kanal to 8 kanal