Progress of the Project

  • Sialkot Tennery Zone is indispensable for the survival and upgradation of the Leather Sector of Pakistan.
  • Sialkot city is fetching Major part of foreign exchange in Leather Sector.
  • Sialkot Tannery Zone infrastructure ready to house the Tanneries in the Zone.
  • Effluent Treatment of STZ is first of its kind in Pakistan have seprate primary treatment for beam house effluent and post Tanning effluent, which is 83% already completed. The installation of machines and equipment is in progress.
  • The drainage system is 100% complete. All the drains are constructed in connecte to have a long life. The total length of drains is 35 km with segregated channels to carry beam house, chrome, and post Tanning effluents.
  • The road structure having a length of 15 KM is complete, and only the black top is left.
  • The solid waste management is part of STZ, the technology of hazardous management landfill is already firmed up.
  • Construction on 225 plots is in progress.
  • There are a total 540 plot holders in STZ, 90% are SMEs having plot sizes of 01 Kanal to 8 kanal

100 % Completion of

  • Boundary Wall
  • Main Gain
  • Site offices / Stores
  • Flood Protection Embankment
  • Annual Cleaning and Capacity raising of Dugri Drain- II
  • Plotting of Zone