ESTABLISHMENT OF COMMON EFFLUENT TREATMENT PLANT

On the basis of the survey results, Under GEF Project The conceptual  design of CETP has been got prepared by UNIDO expert, this conceptual design has already been shared with all the stakeholders Tanners, SCCI member, District Government Authorities, Environment Protection Agency Punjab and got endorsed by all the stakeholders.

  • Designing Completed. (UNIDO-GEF Funded)Detail
  • The Contract for Civil Works has been awarded and civil works are under-way. The civil works are delayed because of non-payments from TDAP/EDF side. However now the payments are streamlined and it expected that civil works will be completed by June 2024. (Govt of Pak- EDF/TDAP + STAGL funded)

Release of Works Order to Lowest Bidder for Electro-Mechanical Works of CETP. Most of the equipment has manufactured. Now the shipments from abroad have started arriving at site (09 out of 10# of shipments have arrived). The mechanical installation works have been started at site. (UNIDO-GEF + STAGL funded)